ACTION REQUIRED: NEXRAD Level II Maintenance Notification (Thursday, August 10th) (RDS)



The ROC will be changing the IP address of the RDS server on Thursday, August 10, 2023. This is not a change to the NL2 system or software, but rather a network device beyond our control.

Start Time: 10:00 AM (CDT) (15:00 UTC) Thursday, August 10, 2023
Duration: 30 minutes
Event: IP address change (RDS/Norman)
Location: Radar Operations Center, Norman, OK

Clients must change the IP address of RDS to continue receiving data. We recommend that clients use the dns name (rds.nexrad.noaa.gov), where possible. You may begin using the dns name now, and do not have to wait until August 10. If an IP address is required on your system, please update LDM configurations to reflect the new address shown below on the coordinated date.

RDS current IP address: x.x.24.16
RDS new IP address: x.x.117.79

Please keep BOTH NL2 connections (TDS/Ashburn & RDS/Norman) up to avoid data flow interruption. The TDS/Ashburn is not affected by this maintenance action.  No change is required to continue to receive data from the TDS.

If you have any questions about this change, please contact address@hidden.

National Level II (NL2) status information via weather.gov is available (https://www.weather.gov/nl2)

NEXRAD View - WSR-88D monitoring by site location
SPG View - TDWR Status via the NWS SPG
SERVER View - NL2 server & Network status (Shows site connectivity and Ashburn vs Norman Data flow)
CONTROL View - Shows data latency for each NL2 server
LDM View - Level II Data flow from site
NPN View - Shows FSL2 data from the NOAA Profiler Network

If there is any emergency associated with Level II data flow noted during this event, support can be reached at (405) 820-3646 or address@hidden.