[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

NEXRAD Level II Maintenance Notification (Friday, 04/08/2022)(RDS Path)



Verizon will be performing corrective software maintenance on equipment to provide improved network reliability that will impact NEXRAD Level II (NL2) data flow from the ROC Distribution System in Norman.

Site Impacted: Radar Operations Center, OK     Start Date-Time: 04/08/2022 00:01 CDT(05:01 Am GMT)
Stop Date-Time: 04/08/2022 06:00 CDT(11:00 Am GMT)
Planned Circuit Downtime: 05 Minute(s)

The data path via Silver Spring is not part of this activity.  No service interruption via the TDS path is anticipated.


Please keep BOTH NL2 connections (Silver Spring & Norman) up to avoid data flow interruption.


If there is any emergency associated with Level II data flow noted during this event, I can be reached at (405) 820-3646 or or address@hidden.


Thank you,
Michael Weeks
Radar Operations Center/Software Engineering
405-820-3646