[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

NEXRAD Level II Maintenance Notification - Maintenance Extended (3/26/2021 thru 4/12/2021) (TDS Path )



Network equipment continues to be powered down for safety reasons in Silver Spring.  This impacts the data flow of the National Level II (NL2) system TDS path.  


Start Time: 12:30 AM (Eastern time) Tuesday Mar 9th, 2021
Finish Time:  5:00PM (Eastern Time) Friday April 12th, 2021 (ESTIMATED)
Duration: 34 Days
Event: Facility Power Issue (Silver Spring)


The maintenance effort to restore Silver Spring power is currently estimated to take 34 days to complete and will affect Data flow of the "Silver Spring/TDS Level II Path".

The Data Path via Norman, OK/RDS server is not part of this activity. (No service interruption via RDS path is anticipated.)

Please keep BOTH NL2 connections (Silver Spring & Norman) up to avoid data flow interruption.  National Level II (NL2) status information via 
weather.gov is available.

https://www.weather.gov/nl2/

NEXRAD View - WSR-88D monitoring by site location
SPG View - TDWR Status via the NWS SPG
SERVER View - NL2 server & Network status (Shows site connectivity AND
Silver Spring vs Norman Data flow)
CONTROL View - Shows data latency for each NL2 server
LDM View - Level II Data flow from site
NPN View - Shows FSL2 data from the NOAA Profiler Network

If there is any emergency associated with Level II data flow noted
during this event, support can be reached at (405) 820-3646  or
address@hidden

--
William Greenwood
Computer Specialist
WSR-88D Radar Operations Center